The entrance ramp from Fourth Street to I-75 southbound, and the exit ramp from I-75 southbound to Fourth Streetwill be closed for 45 days to allow for soil stabilization, drainage work and paving on the ramps.
More work on the I-75 reconstruction project starts today.
The entrance ramp from Fourth Street to I-75 southbound, and the exit ramp from I-75 southbound to Fourth Streetwill be closed for 45 days to allow for soil stabilization, drainage work and paving on the ramps.
Following the Labor Day holiday, both ramps to and from Fourth Streetwill be closed for 30 days.
Traffic on I-75 in the area of the bridge will be maintained with two lanes in each direction during the ramp closures- with occasional nighttime lane closures as well.